Today I worked on the wiring and the cable management inside the case. This meant I had to make
signal and power wires for all the drives, and eventually wire up the PSU’s to power. I also took the time
to install all of my fans, and the signal generator meaning all that is left is to work on the computer and
the wiring. At the end of the day I started to do work on the internal power cables, They are almost done
I think that I will finish them up tomorrow and then go and start to work on the base.
signal and power wires for all the drives, and eventually wire up the PSU’s to power. I also took the time
to install all of my fans, and the signal generator meaning all that is left is to work on the computer and
the wiring. At the end of the day I started to do work on the internal power cables, They are almost done
I think that I will finish them up tomorrow and then go and start to work on the base.
Day 8
Today I did start work on the base of the CNC, I went down to the metal shop to start setting things up,
and to move my materials over. This took a lot of time as I had to do a lot of setup work on the horizontal
mill to be able to accommodate parts of the size that machining. I had to indicate and line up to two vises
gapped by the entire 30 inch table. I also put the cutter I am going to be using on the machine, as well
as setup the spray coolant system that I designed last year to cool the cutting operation. Afterwards I
went back and continued to clean up the wiring as well as start to wire my spindle as well as start the process of getting everything booted
and to move my materials over. This took a lot of time as I had to do a lot of setup work on the horizontal
mill to be able to accommodate parts of the size that machining. I had to indicate and line up to two vises
gapped by the entire 30 inch table. I also put the cutter I am going to be using on the machine, as well
as setup the spray coolant system that I designed last year to cool the cutting operation. Afterwards I
went back and continued to clean up the wiring as well as start to wire my spindle as well as start the process of getting everything booted
Day 9
Today I primarily focused on the frame, I spent a bunch of time down in metal shop working on getting
the horizontal mill ready for action and then spent time cleaning up my steel. In the afternoon I
worked on the software of the CNC. I then took some time to start to cut pieces to length. The next
step would be to start machining the surfaces I'm going to weld.
Day 10
Today I worked on doing more wiring. I primarily focused on the VFD, and the signal board I spent
most of the day going through documentation to ensure that I have everything hooked up correctly,
and I was making sure that I had everything I needed to get the electronics running. This included me
having to buy a better spindle cable because the one I was planning on using was not rated for the
electrical interference.
most of the day going through documentation to ensure that I have everything hooked up correctly,
and I was making sure that I had everything I needed to get the electronics running. This included me
having to buy a better spindle cable because the one I was planning on using was not rated for the
electrical interference.
Day 11
Today I worked worked on finishing up the wiring of the control box, and took the time to order the rest
of the power electronics I need, such as my PSU for my signal generator. The system should be ready
to boot next week when we can start wiring the motors in the frame. This week was productive,
although I am confused as to where my surface plate is, It was supposed to be shipped already, but I
have not seen it yet. I will have to call the company on Monday.
of the power electronics I need, such as my PSU for my signal generator. The system should be ready
to boot next week when we can start wiring the motors in the frame. This week was productive,
although I am confused as to where my surface plate is, It was supposed to be shipped already, but I
have not seen it yet. I will have to call the company on Monday.
Week 2
This week was productive, although I am confused as to where my surface plate is, It was supposed to
be shipped already, but I have not seen it yet. I will have to call the company on Monday. I think that
the wiring is going super well and the frame is starting to come together. I will be spending a
considerable time in the metal shop over the rest of the project though.
be shipped already, but I have not seen it yet. I will have to call the company on Monday. I think that
the wiring is going super well and the frame is starting to come together. I will be spending a
considerable time in the metal shop over the rest of the project though.
Comments
Post a Comment