Skip to main content

Wednesday - Saturday


Today I worked on in metal shop getting everything ready to weld. This is a critical and time consuming
process because I need to ensure that the frame is square and straight. This involves a lot of machine
work on top of welding. I am getting it done though the X axis frame is coming along well, and I think that
I should be ready to weld by around Saturday.


Today I worked on finishing up the limit switch wires in the morning and started getting the computer
system set up. I spent the afternoon machining my steel to length in the metal shop. I should be able to
weld the top rails by tomorrow, and then I can machine them and weld them up to my other bars. Also
the surface plate should be here tomorrow.


The surface plate came today, and I welded the top rails, hopefully will be able to clean up the welds,
and then start drilling the parts. It is gonna take some machining to make sure everything is square and
flat. This is critical as to make sure that the rails are parallel, because if they aren't they wont run
properly.  The surface plate is cool though I have its rating and deviation. Its very flat, I have it's deviation
in nanometers. I was very hard to get in the shop though enlisting the help of a dolly, and 4 people to lift it
up to the table.


Today I did set up the fly cutter and started to clean up my rails. I am doing this to have a reference to
make sure that the welds are done square. I am planning on tack welding it on the surface plate. The fly
cutter worked really well, and the part is very flat. I will have more fly cutter work to do but hopefully I
can get everything drilled by around Monday.

This week I spent a lot of time in the metal shop working on the frame. It was a little slower going than I
thought it was going to be, but it was really productive I think that the machining has been going along
really well, and I am able to hold less than 3 thousandths of an inch across the rails, which is good
considering they are 31.5 inches long. Everything is getting to be really straight and square I should be
able to weld the rails up sometime soon. The next step is drilling and tapping, which will take a while,
but everything is coming out really good, and the machining is square and flat.

Comments

Popular posts from this blog

CNC Milling Machine Project Day 4 Today I started out working on finalizing the fan mounts. This will include going to the metal shop to remove some of the aluminum where it would interfere with the airflow of the fan. After I finished my work on that I went down to the tech center to get some old scrap ethernet wires that I will be using as my stepper signal wires. I then started trying to wire up and example driver with my hardline cable, this was hard as the cables were brittle and would sometimes break off in the terminal blocks if I moved them around too much. I think that I might go to start using the patch cable with soldered ends. This would make the connection way more durable because it would be more flexible. Tomorrow I will be able to wire up and hopefully start testing stepper motors proving I find a way to wire the AC power to the stepper’s PSU.   
CNC Milling Machine Project Day 2 Today I worked on making the case for my electronics. I spent the morning at the woodshop installing a wood back panel in the PC case. After that I went back to shirley hall and reinforced the back panel and screwed it to the case. After that I spent time designing mounts for all my electronics inside the case. I also took the time to do some more design work on the CNC, where I started to lay out my motor mounts, and my electronics mount. I spent the rest of the afternoon researching what the wiring work the I will need to do, and also how to wire the PSU’s to mains power.